Identified dependencies, that serves as a foundation for task sequencing. |
|
https://en.wikipedia.org/wiki/Work_breakdown_structure |
|
|
|
IDEA: I'm not happy about have two separate arrays for the task_ids and the explanations. |
|
There should be 1 task id and 1 explanation per dependency. |
|
Currently there can be N task ids and M explanations, where N != M. This is not good. |
|
|
|
IDEA: Label each dependency with its type (FS, SS, FF, SF). |
|
- Finish-to-Start (FS): Task B cannot start until Task A is finished (most common). |
|
- Start-to-Start (SS): Task B cannot start until Task A starts. |
|
- Finish-to-Finish (FF): Task B cannot finish until Task A is finished. |
|
- Start-to-Finish (SF): Task B cannot finish until Task A starts (least common). |
|
|
|
IDEA: Missing Dependencies. |
|
I asked Gemini to check the json file containing the dependencies, and it did spot some missing dependencies. |
|
So I need an extra LLM that can go identify if there are more missing dependencies. |
|
""" |
|
import os |
|
import json |
|
import time |
|
from math import ceil |
|
from typing import List, Optional |
|
from uuid import uuid4 |
|
from dataclasses import dataclass |
|
from pydantic import BaseModel, Field |
|
from llama_index.core.llms.llm import LLM |
|
from src.format_json_for_use_in_query import format_json_for_use_in_query |
|
|
|
class TaskDependencyDetail(BaseModel): |
|
""" |
|
Details about the prerequisites for a task. |
|
""" |
|
dependent_task_id: str = Field( |
|
description="UUID that uniquely identifies a major phase or a subtask." |
|
) |
|
|
|
depends_on_task_id_list: list[str] = Field( |
|
description="List of UUIDs that are prerequisites for this task." |
|
) |
|
|
|
depends_on_task_explanation_list: list[str] = Field( |
|
description="List of explanations why these tasks must be completed before this task." |
|
) |
|
|
|
class DependencyMapping(BaseModel): |
|
""" |
|
Understanding the dependencies between tasks is crucial for effective project scheduling and |
|
ensuring that prerequisites are met before commencing subsequent activities. |
|
""" |
|
task_dependency_details: list[TaskDependencyDetail] = Field( |
|
description="List with dependency mappings between tasks." |
|
) |
|
|
|
QUERY_PREAMBLE = f""" |
|
Find the 10 most critical important task dependencies. Don't attempt making an exhaustive list. |
|
|
|
Understanding how tasks relate to each other is crucial for accurate timeline planning. |
|
Dependencies determine the sequence in which tasks must be completed. |
|
|
|
Types of Dependencies: |
|
• Finish-to-Start (FS): Task B cannot start until Task A is finished. |
|
• Start-to-Start (SS): Task B cannot start until Task A starts. |
|
• Finish-to-Finish (FF): Task B cannot finish until Task A finishes. |
|
• Start-to-Finish (SF): Task B cannot finish until Task A starts (rarely used). |
|
|
|
Example Dependencies: |
|
• Land Acquisition must be completed before Permitting and Approvals can begin. |
|
• Permitting and Approvals must be completed before Design and Engineering starts. |
|
• Procurement of materials can begin once Design and Engineering is underway. |
|
|
|
""" |
|
|
|
@dataclass |
|
class IdentifyWBSTaskDependencies: |
|
""" |
|
Enrich an existing Work Breakdown Structure (WBS) with details about dependencies between tasks. |
|
""" |
|
query: str |
|
response: dict |
|
metadata: dict |
|
|
|
@classmethod |
|
def format_query(cls, plan_json: dict, wbs_level2_json: list) -> str: |
|
""" |
|
Format the query for creating a Work Breakdown Structure (WBS) level 2. |
|
""" |
|
if not isinstance(plan_json, dict): |
|
raise ValueError("Invalid plan_json.") |
|
if not isinstance(wbs_level2_json, list): |
|
raise ValueError("Invalid wbs_list.") |
|
|
|
query = f""" |
|
The project plan: |
|
{format_json_for_use_in_query(plan_json)} |
|
|
|
The Work Breakdown Structure (WBS): |
|
{format_json_for_use_in_query(wbs_level2_json)} |
|
""" |
|
return query |
|
|
|
@classmethod |
|
def execute(cls, llm: LLM, query: str) -> 'IdentifyWBSTaskDependencies': |
|
""" |
|
Invoke LLM to identify task dependencies from a json representation of a project plan and Work Breakdown Structure (WBS). |
|
""" |
|
if not isinstance(llm, LLM): |
|
raise ValueError("Invalid LLM instance.") |
|
if not isinstance(query, str): |
|
raise ValueError("Invalid query.") |
|
|
|
start_time = time.perf_counter() |
|
|
|
sllm = llm.as_structured_llm(DependencyMapping) |
|
response = sllm.complete(QUERY_PREAMBLE + query) |
|
json_response = json.loads(response.text) |
|
|
|
end_time = time.perf_counter() |
|
duration = int(ceil(end_time - start_time)) |
|
|
|
metadata = dict(llm.metadata) |
|
metadata["llm_classname"] = llm.class_name() |
|
metadata["duration"] = duration |
|
|
|
result = IdentifyWBSTaskDependencies( |
|
query=query, |
|
response=json_response, |
|
metadata=metadata |
|
) |
|
return result |
|
|
|
def raw_response_dict(self, include_metadata=True, include_query=True) -> dict: |
|
d = self.response.copy() |
|
if include_metadata: |
|
d['metadata'] = self.metadata |
|
if include_query: |
|
d['query'] = self.query |
|
return d |
|
|
|
if __name__ == "__main__": |
|
from llama_index.llms.ollama import Ollama |
|
|
|
basepath = '/Users/neoneye/Desktop/planexe_data' |
|
|
|
def load_json(relative_path: str) -> dict: |
|
path = os.path.join(basepath, relative_path) |
|
print(f"loading file: {path}") |
|
with open(path, 'r', encoding='utf-8') as f: |
|
the_json = json.load(f) |
|
return the_json |
|
|
|
plan_json = load_json('002-project_plan.json') |
|
wbs_json = load_json('005-wbs_level2.json') |
|
|
|
query = IdentifyWBSTaskDependencies.format_query(plan_json, wbs_json) |
|
|
|
model_name = "llama3.1:latest" |
|
|
|
|
|
llm = Ollama(model=model_name, request_timeout=120.0, temperature=0.5, is_function_calling_model=False) |
|
|
|
print(f"Query: {query}") |
|
result = IdentifyWBSTaskDependencies.execute(llm, query) |
|
|
|
print("Response:") |
|
response_dict = result.raw_response_dict(include_query=False) |
|
print(json.dumps(response_dict, indent=2)) |
|
|